Project summary:

Dualling of the A350 at Chippenham between Bumpers and Brook roundabouts.



Current project status:

Shortlisted by Board: 2014
Funding Approved by Board: July 2014
Outline Business Case approved: July 2014
Full Business Case approved by Board: July 2014
Construction Due to Start: July 2015
Construction Due to Complete: March 2016