Project summary:

Road junction improvements to enable the expansion of the Dyson Technology Park and interdependent developments. Accommodating increased traffic movements, improving journey time reliability and creating up to 3,000 jobs in total



Current project status:

Shortlisted by Board: 2014
Funding Approved by Board: July 2014
Outline Business Case approved: July 2014
Full Business Case approved by Board: July 2014
Construction Started: July 2015
Construction Completed: July 2016