Project summary:

Major improvement works to the Greenbridge roundabout junction as part of a programme to improve major routes into Swindon.

Investment:

£5,300,000

Current project status:

Completed
Shortlisted by Board: January 2014
Funding Approved by Board: July 2014
Outline Business Case approved: July 2014
Full Business Case approved by Board: July 2014
Construction Started: April 2016
Construction Completed: January 2017

Additional Information:

Major improvement works to the Greenbridge roundabout junction as part of a programme to improve major routes into Swindon to keep pace with the future development of the New Eastern Villages.

Local Growth Fund Allocation:
£2,000,000