yarnbrook-west-ashton-2

Project summary:

To provide a new link road between the New Eastern Villages and the Commonhead roundabout in Swindon.

Investment:

£20,949,000

Current project status:

In Progress
Shortlisted by Board: January 2014
Funding Approved by Board: June 2014
Outline Business Case approved: March 2019
Full Business Case approved by Board: July 2019
Construction Started: November 2019
Construction Completed: March 2021

Additional Information:

To provide a new link road between the New Eastern Villages and the Commonhead roundabout in Swindon, relieving demand on the existing highway infrastructure to the north.

Local Growth Fund Allocation:
£11,600,000