A419

Project summary:

Traffic management measures and junction improvements within East Swindon as part of the New Eastern Villages development.

Investment:

£2,613,000

Current project status:

In Progress 
Shortlisted by Board: January 2014
Funding Approved by Board: July 2014
Outline Business Case approved: March 2019
Full Business Case approved by Board: August 2019
Construction Started: January 2020
Construction Completed: March 2021

Additional Information:

Local Growth Fund Allocation:
£2,000,000