Project summary:

White Hart Junction provides a key gateway into Swindon, connecting the A420 with the A419.

Investment:

£32,800,000

Current project status:

In Progress
Shortlisted by Board: January 2014
Funding Approved by Board: June 2014
Outline Business Case approved: March 2019
Full Business Case approved by Board: March 2019
Construction Started: January 2020
Construction Completed: March 2021

Additional Information:

The purpose of the scheme is to improve capacity and traffic management, and mitigate the impact of the New Eastern Villages development.

Local Growth Fund Allocation:
£22,500,000