Swindon-Bus-Exchange-4

Project summary:

Relocation of Swindon's bus station from its current location off Manchester Road to the Cheltenham Street surface car park.

Investment:

£6,000,000

Current project status:

Full Business Case approved by board
Shortlisted by Board: January 2014
Funding Approved by Board: January 2015
Outline Business Case approved: March 2019
Full Business Case approved by Board: June 2019
Construction Started: June 2021
Construction Completed: March 2021

Additional Information:

Local Growth Fund Allocation:
£3,000,000