superfast

Project summary

To procure and deploy an Ultrafast / NGA fibre broadband solution in Wiltshire.

Local Growth Fund Allocation:
£1,000,000

Total Investment:

£3,000,000

Current project status:

Shortlisted by Board: 2014
Funding Approved by Board: July 2014
Outline Business Case to be  approved: Sept 2018
Construction Due to Start: March 2018
Construction Due to Complete: December 2019

Resources