Project summary

Provide the fourth and final access point required to deliver the Wichelstowe housing development

Local Growth Fund Allocation:
£22,900,000

Total Investment:

£118,196,000

Current project status:

Shortlisted by Board: 2014
Funding Approved by Board: July 2014
Outline Business Case approved: May 2018
Full Business Case to be approved by Board: March 2019
Construction Due to Start: July 2019
Construction Due to Complete: March 2021